Transmission Line Approved
(2008-06-02)
(WOUB) - The Ohio Power Siting Board approved the construction of a 138-kilovolt transmission line in Pike County.

According to a news release, the line will help prevent overloads of existing transmission facilities and allow for growth in Southern Ohio.

The 6-mile line will connect a substation in Piketon to the Lick-Waverly transmission line and will be owned and operated by AEP.