More details on I-64 reconstruction released
(2007-01-22)
I-64/I-170 interchange.
(St. Louis Public Radio) - The firm that's in charge of the reconstruction of Interstate 64 in St. Louis is releasing more details about the project.

Gateway Constructors say the first phase of the $535-million project will begin next month with the demolition of several houses in Sheridan Hills, at the northeast corner of I-64 and I-170.

Then, the rebuilding of the I-170/I-64 interchange begins in earnest in March, with three lanes of I-170 reduced to two in each direction between I-64 and the Galleria Parkway.

Also in March, ramps on the south side of the Galleria Parkway and ramps from Hanley Road to westbound I-64 will be closed.

April will see work starting on the Kingshighway intersection.

The entire project is expected to be completed by 2010.

I-64 Reconstruction Schedule

February 2007
- Demolish homes in Sheridan Hills (I-64/I-170)
March 2007
- Reduce I-170 to two lanes in each direction from I-64 to Galleria Pkwy.
- Ramps on south side of Galleria Pkwy. closed permanently
- Both ramps from Hanley Rd. to westbound I-64 closed for rebuild
April 2007
- Rebuild starts at I-64/Kingshighway; reduce Kingshighway to two lanes in each direction
Later 2007
- Bridges close at Tamm Av., Bellevue Av., Boland Av., and Highland Terrace for replacement
PUBLIC HEARINGS ON CONSTRUCTION
(all run 4-7 p.m.)
- Jan. 30: Science Center (Planetarium)
- Feb. 6: Brentwood Middle School
- Feb. 13: County Library on Lindbergh